
The following drawings and text are copied directly from DEB Design Boiler Plan I
"Start of Plan Sample"
This will be a very rewarding project, if you would like an outside
woodburning stove, but are concerned about the cost of commercial units. This stove will
cost $ 500 - $ 800 to build, as specified, using all new steel and components, however it
can be built for much less, if salvaged materials are used. You should also budget an
additional $200 - $300 to plumb the completed unit into your existing heating system.
These costs will vary, depending on your system design. This stove features:
* A large 35 cubic ft. firebox
* A 200 gallon capacity waterjacket
* A large, water filled, loading door
* Automatic, adjustable, thermostatic control of the water jacket temperature
* A blower induced, powered damper, draft control system
* 12-36 hour burn times, between loading
* A baffled flue design providing optimum efficiency
* A complete design requiring no additional housing
* An open vent design, preventing the possibilities of dangerous pressures
* The ability to burn any type of wood without the worry of creosote build-up and
potential chimney fire. This plan could also be modified to:
* increase the stove size
* add additional flue baffling
* use thicker steel
The size of this unit was determined by prototype testing, to see what size firebox would
be required, to heat a 2300 sq. ft. house, plus the full basement, for 24 hours, in a
typical Wisconsin climate.
Included in this plan set is:
* A complete material list, including sources
* Construction tips learned from building prototypes
* Step by step construction drawings
* Electrical and plumbing schematics
* Start up and maintenance instructions
This project may seem challenging at first, but with time and patience, you'll be able to
build your own outdoor heating plant, to meet your home heating needs. You can then take
comfort knowing that, your home heating bills will remain controllable.
Copyright 2000 DEB Design. DEB Design takes no responsibility for the
use of any of the materials or methods described neither in this publication nor for the
products thereof

TABULATED STEEL LIST |
This List Includes All the Numbered Steel Components from the Materials List |
Steel Plate Minimum .125 inch thick (11 guage) .250 preferred |
| 1) 2 PCS. 51 inch X 50 inch |
| 2) 5 PCS. 36 inch X 48 inch |
| 3) 2 PCS. 3-3\4 inch X 48 inch |
| 4) 2 PCS . 4 inch X 48 inch |
| 5) 2 PCS. 52 inch X 44 inch |
| 6) 2 PCS. 50 inch X 44 inch |
| 7) 2 PCS. 36 inch X 44 inch |
| 8) 1 PC. 34 inch X 34 inch |
| 9) 2 PCS. 3-3\4 inch X 36 inch |
| 10 3 PCS. 2 inch X 36 inch |
| 11) 4 PCS. 1-1/2 inch X 34 inch |
| 12) 4 PCS. 1-1\2 inch X 6 inch |
| 13) 2 PCS. 4 inch X 4 inch |
| 14) 4 PCS. 1 inch X 36 inch |
| 15) 1 PC. 6 inch X 38 inch |
ANGLE IRON |
| 1) 4 PCS. 3\16 inch X 1 inch X 38 inch long |
| 2) 2 PC. 3\16 inch X 1-1\2 inch X 41 inch long |
| 3) 1 PC. 3\16 inch X 1-1\2 inch X 44 inch long |
| 4) 2 PCS. 1\4 inch X 2 inch X 1-1\2 inch long |
| 5) 2 PC. 1\8 inch X 1-1\2 inch X 38 inch long |
TUBING\PIPE |
| 1) 1 PC. 1\4 inch X 8 inch X 36 inch LONG |
All tolerances are + or - 1\16 inch |
FREQUENTLY ASKED QUESTIONS AND ANSWERS
Question:
How does the outside wood stove/boiler built from this plan work?
Answer:
This stove is basically, a very large firebox that is completely surrounded by water.
A thermostat on the boiler waterjacket, energizes and de-energizes a forced air, powered
damper and draft assembly, to maintain a constant user-set boiler water temperature. A low
wattage pump moves this heated water to the house and back. The electricity to power this
setup costs the author, about $10.00 per month at .06 KH.
Question:
What is the design of the delivery system that supplies the heated water to the house?
Answer:
I used 1-1/4" galvanized pipe that I obtained for free. Otherwise I would
recommend, using 1"flexible copper or PEX tubing. Use long enough coil lengths to
eliminate underground splices. The tubing should be well insulated with lengths of thick
foam, pipe or fiberglass, insulation, or encased in 4" PVC, non-perforated sewer
pipe, to keep moisture out of the pipe insulation. Do not use black poly pipe. It cannot
take the heat, and will eventually crack. These supply and return waterlines, should be
buried at least 12" deep.
Question:
How often do you have to fill the fire box?
Answer:
That will depend on the outside temperature, and the size and insulation properties of
your house. With my house (2300 sq. ft. plus a full basement) here in Wis., I fill the
stove twice a day using softwood, until the temperature gets down to 0 degrees Fahrenheit.
At that point I burn hardwood, but still only load twice per day. When the temperature is
at, or above 20 degrees, once per day is sufficient.
Question:
Can I use the boiler for other heating applications such as heating domestic hot
water?
Answer:
Yes. It can be used to heat domestic hot water, a swimming pool as I do, or a hot
tub/spa. This requires only a liquid to liquid heat exchanger, plans for, which are
available from DEB Design.
Question:
I have a forced air furnace in my house. Can this stove work in this application?
Answer:
Yes. There are 3 main ways this boiler can be used with any existing furnace system:
1) In a hydronic (hot water system) the hot water could be pumped directly to the boiler
distribution manifold, and delivered to the various zones of the system as dictated by the
zone thermostats. This is the method I currently use.
2) In a hydronic system, a liquid to liquid heat exchanger could be installed. The wood
boiler water would be pumped into the exchanger, which would then heat the house system
water, when the zone thermostats open and allow water flow through the exchanger.
3) In a forced air system, the boiler water would be pumped continuously through a liquid
to liquid heat exchanger that is installed in the furnace plenum, just like an air
conditioning "A" coil. A simple control is installed to keep the furnace burner
off, if the boiler supply water is
hot enough. Then, when the house thermostat calls for heat, only the furnace blower is
energized. In methods 2 and 3, the exchangers serve two purposes:
1) Supply heat to the house heating circuit.
2) Supply heat to the wood boiler circuit, too prevent freezing when the boiler fire goes
out, if no antifreeze is used.
DEB Design offers construction plans for a liquid to liquid heat exchanger. Liquid to air
heat exchangers are available through most plumbing and heating retailers.
Question:
Does it take superhuman welding skills to weld this boiler? I am interested in
building such a outdoor heating apparatus. I would like to know what welding skills are
necessary as I am a novice.
Answer:
I feel average welding skills are required to complete this project. It is constructed
from cold rolled steel with mostly long straight 90 deg. butt welds. If you don't have
average skills, I recommend you have a qualified friend, or even a welding shop, weld it
for you. For a budgetary quote, plan on 60 hrs. to complete the welding.
Unfortunately, if you are considering paying someone to weld or build your
stove, you might just as well purchase a commercially built stove.
Question:
How easy is it to change the plans? Could 7 gauge steel be used? Can the plans be
modified to include a slide out ash pan and grate system?
Answer:
This design is real flexible. The material list specifies the component sizes and
assigns each piece a number. The plan drawings explain the assembly sequence, and show how
the numbered pieces fit together. Using thicker steel would not be any problem. Extending
the firebox length to 6', as an example, would involve adding 24" to the length of
the appropriate pieces. This could take a bit of studying, however, it could easily be
done. I once thought about installing an ash pan and did use a grate system, for a while.
The grate didn't stand up very well, so I finally just left the ashes to serve as the bed.
This has worked out quite well for me. I usually remove the ashes every 2 to 3 weeks. I do
this prior to a reload session. I push the embers over to one side, and then shovel out
half the box, and then repeat with the other half. Once done I refill the firebox. The
residual embers easily restart the fire. It does get a bit smoky on occasion, but
otherwise it's quite trouble free. If an ash pan/grate system was desired, I feel that one
could be designed and installed, without too much trouble.
Question:
Some heaters use an insulated door instead of a water filled door. Wouldn't that be
simpler?
Answer:
Yes, it probably would be simpler. I was concerned about safety, and insuring that no
exterior boiler surfaces became hotter than the boiler water temperature. This also could
be left to the builder's discretion.
Question:
What would be the life expectancy of the 11 gauge steel.
Answer:
That will depend on how leak free the fire box is made. The enemy here is rust, not
heat. If the inside of the firebox stays moisture free, I would expect it to last many
years. I also think that using a rust inhibitor (automotive) in the boiler water, would
help promote a long boiler life.
Question:
The first thing that I was wondering is how do you fill your boiler with water? Do you
fill it with a hose?
Answer:
I have a water supply line plumbed into the circuit, inside my house.
Question:
How many gallons do you think you fill each week?
Answer:
I usually only have to add a gallon or so each week.
Question:
Have you thought of installing anode rods similar to water heaters?
Answer:
No, but that's an excellent idea. They would need to be installed along either of the
sides where there is enough depth.
Question:
I am concerned about heat loss through the door of the unit. Any suggestions on
insulation in the door to take the place of the water? Possibly vermiculite?
Answer:
The primary reason the door is water filled, is safety. This unit will sit outside,
probably unprotected. Using water as a coolant will keep the fire door at a more
reasonable temperature. The secondary reason for a water filled door is to keep it from
warping under high fire/heat conditions, burning pallets, as an example. If the door were
to warp under these conditions, you would lose your draft control, and end up with a run
away stove, a very undesirable condition. I know it's more complicated with a water filled
door, but I think the peace of mind is worth it. My advice in this matter would be to keep
the water filled door, but use vermiculate insulation, as you suggested.
Question:
Would four or five pieces of metal tubing run horizontally in the top of fire box be
an easy way to improve efficiency?
Answer:
It might. There are any number of ways to improve the efficiency of the design. The
plan, as built, was meant to be a starting point, for stove builders. More capable and
advanced builders, could easily add modifications of their own.
Question:
Wouldn't insulation put under the floor of the unit help hold heat.
Answer:
Yes, It would. Perhaps 1" or 2" foam insulation could be safely used here.
Question:
In your design, your supply and return lines both go to or near the top of the boiler.
Why don't you return to the bottom of the boiler?
Answer:
This method provides protection in the event of a major, rubber, door hose break. If
the outlet is positioned properly, the boiler water level would only drop to 1" above
the firebox, which would keep water above the thermostat level. This would then keep the
stove from thermal run-away, and subsequent destruction, and/or possible fire.
Question:
In your design, you weld spacers on the side pieces to make up the baffle system
layout. Would it be better to cut the boiler sides out in one piece?
Answer:
Yes, probably, but this method allows all the parts to be sheared by the steel
supplier.
Question:
Many commercially distributed wood boilers boast a firebrick lining in the firebox.
Your plan doesn't. Do you recommend it for your boiler design?
Answer:
I don't know what the advantage of the firebrick would be in my design.
Question:
I am interested in ordering plans for a wood stove-boiler. Can you tell me the
difference between Plan I and Plan II?
Answer:
Boiler Plan I is made with all new steel components. It is quite flexible and more
efficient, but more costly, and complicated to build, than Boiler Plan II. Boiler Plan II
is made with tanks and fuel oil drums, which can be salvaged locally. It is cheaper
and
easier to build, but is not as flexible as Boiler Plan I. It would be a good
"starter" wood boiler.
Question:
Do the plans show how to hook up the boiler to a forced air heating system?
Answer:
No, the plans provide details for a hydronic system only, including details of the
delivery system. You should consult a heating contractor for that phase of the project.
Question: If the inside of the fire box and flue baffle system become coated with
creosote wouldn't this act as insulation and rob the boiler of efficiency?
Answer: Yes, probably, but the design of the firing system uses a forced air
blower, resulting in high flue temperatures to minimize the build-up.
Question:
Are there any provisions in your design to facilitate flue baffle access for cleaning?
Answer:
In Boiler Plan I the baffles can be accessed for cleaning. Boiler Plan II does not
contain a baffle system.
Question:
Have you found creosote fouling to be a problem with your set up?
Answer:
To date I've had no problem at all.
Question:
I'm somewhat reluctant to build a boiler such as this as I'm not an experienced
welder. What are your thoughts on this?
Answer:
You might want to consider Boiler Plan II. It's easier, and cheaper to build than
Boiler Plan I and would provide you with valuable experience, should you ever want to
build a more complex version.
Question:
What is the difference between a closed system and an open system?
Answer:
A closed loop system is not vented to the outside atmosphere (such as a hydronic
heating system) while an open system is.
Question:
What advantages and disadvantages do they each have?
Answer:
The main advantages of a closed loop are:
1) There will be very little oxygen in the water, which can shorten heating system component
lives. (pumps, valves, etc.)
2) There won't be any evaporation of the boiler water. The main advantage of an open
system is that the components do not have to be as strong to withstand the higher
pressures prevalent in a closed system.
Question:
Do you have any plans for a system that holds less water?
Answer:
No, but the plans can be easily modified by the builder.
Question:
Can you use a boiler to heat two buildings?
Answer:
Yes, all you do is run a plumbing (including pump and thermostat) loop from the boiler
to the building to be heated.
Question:
Can this unit be setup, so that if the fire goes out the gas furnace will take over?
Answer:
I have no direct experience with this type of setup, but it can be done. A liquid to
air heat exchanger is usually installed in the forced air furnace plenum. A thermostat
keeps the forced air furnace ignition circuit from energizing if the incoming water loop
(from the wood boiler) is hot enough. This water loop runs continuously. If the boiler
loop temperature drops, the thermostat would enable the ignition circuit so the house
furnace could heat the house and the boiler through the exchanger and boiler loop. (This
would keep the wood boiler circuit it from freezing until restarted)
Question:
I currently have a 4,600 sq. ft. home with a 430 sq. ft. garage and a 16 by 30 ft.
indoor swimming pool. We are using a 225,000 B.T.U gas boiler to heat our home. This
boiler operates at 18 p.s.i with an expansion tank. Will your wood boiler work with our
present system with the gas boiler used only for a backup?
Answer:
I've estimated the DEB Design plan design boiler at app. 125,000 BTUs. You'd need to
use liquid to liquid heat exchangers to integrate the outside wood stove into your
existing heating system. I've estimated the DEB Design exchanger plan design BTU rating at
app. 50,000, so you'd need at least 5 of the exchangers and a large enough wood boiler to
match your current stove capacity. (Plus a whole lot of wood to fuel it)
Question:
How large of a boiler will I need in the previous question?
Answer:
About twice the size of the plan design, which has a 36 cubic ft. capacity firebox.
(In theory)
Question:
Are the plans for Boiler I and Boiler II different size boilers?
Answer:
No, they have the same size firebox.
Question:
What are the BTU ratings of the plan boilers?
Answer:
Approximately 125,000 BTUs.
Question:
Do you ever, or frequently have problems pushing water with your small ground Grunfos
pump? Have you ever had the situation where your pump won't push air, but it will push
water? Do you have any ideas as to why I am running into so much trouble with the pump
quitting pumping the cycle?
Answer:
Yes, I've had the same problems with air in the lines, especially the first year, when
I used poly pipe for supply and return lines. Leaks will cause this. Also, the Grunfos
pump may not pump water up hill very well. A critical design element is the nipple length,
shown on the "Side View" of Drawing 15. (Size the pipe nipple length to end
1" above the firebox) This creates a fluid locked water circuit, between the boiler
supply and return outlets. Once all the air is purged from the lines, the Grunfos pump can
"move" water continually, with out problems, as long as there are no major water
leaks. If you don't construct the boiler return entry like this, you won't be able to use
a Grunfos pump. You may need a stronger pump. (More electrical power consumption) In my
own installation I placed an old jet pump ahead of the Grunfos pump, that I use for
purging air out of my system. (It also serves as a back up pump)I must always be careful
to insure that at least 1 heat circuit is open, otherwise the pressure from the auxiliary
pump will trip the high pressure relief valve on my natural gas commercial boiler
(usually set at about 30#). As you can surmise, I have my heating systems integrated. Once
all the air is purged from the system, the auxiliary pump is shut off, and the small
circulating can pump just fine. If you are using a radiator as a heat exchanger, the
auxiliary pump should be installed on the return side. This would insure that the radiator
is not exposed to excessive pressure.
Question:
How do I seal around the chimney, high temp silicone?
Answer:
Use a chimney collar. This is a piece of steel that wraps tightly and fastens around
the flue pipe. It flares down and out, a few inches. High temp sealant could be used to
complete the seal between the collar and flue pipe.
"End of plan Sample"