The following drawings and text are copied directly from DEB Design Pool/Spa Heater Plan I
"Start of Plan Sample"
Build a Liquid to Liquid Heat Exchanger to Heat Your Swimming Pool or Spa
This project was developed to be used with an outside wood burning furnace, or a hot water boiler, to heat a swimming pool, or spa. It could also be used for solar heating applications. Commercial versions of these can be expensive, but this exchanger was built for less than $200.
Parts List
1. 1 Pc. 6" dia. x 67" long steel tubing for the outer casing/available from a local steel supplier
2. 2 pcs. 1/8" thick x 6"wide x 6" high steel plate for the endcaps/available from a local steel supplier
3. 18 pcs. 5/8" tube x 1/2" male brass pipe connector/available from your local building center
4. 9 pcs. 5/8" OD x 72" long stainless steel tubing/available from McMaster Carr at http://www.mcmaster.com/ (part # 8989 K79)
5. 1 pc. 3/8 in. pipe coupler/available from your local building center
6. 1 pc. 3/8 in. pipe plug/available from your local building center
7. 2 pcs. 1-1/4" pipe coupling/available from your local building center
8. 2 pcs. 1-1/2" x 24" PVC pipe/available from your local building center
9. 36 pcs. 1/2" MTA plastic hose barbs/available from your local building center
10. 36 pcs. hose clamps/available from your local building center
11. Miscellaneous 1-1/4", 160 psi black poly pipe/available from your local building center
12. Miscellaneous 1-1/4" black iron or galvanized pipe fittings/available from your local building center
Copyright 2000 DEB Design. DEB Design takes no
responsibility for the use of any of the materials or methods
described neither in this publication nor for the products thereof

FREQUENTLY ASKED QUESTIONS AND ANSWERS
Question:"End of plan Sample"